CDU Home | Web Tips | Contacts | Sitemap

Major Projects Office


About us

The Major Projects Office is responsible for the planning, construction and refurbishment of buildings and infrastructure (>$300K) on all campuses of the university.

Services provided

  • Input into funding submissions – the major projects office staff can assist with preparing funding submissions by providing high level costs and construction estimates and timelines.
  • Preparation of conceptual plans and feasibility studies.
  • Planning and construction of approved major buildings and infrastructure.
  • Project management of major capital projects (Projects of $300,000 and above).

Planning and Construction

The Major Projects Office provides a range of planning and construction services to enable University staff to meet the University's Strategic objectives on all campuses.

Project Management Services

The Major Project Office is responsible for the continuous management of the University's Capital Projects for Casuarina, Alice Springs , Katherine and the smaller regional centres. The Project Office can provide advice on provision of new facilities and buildings as well as managing the refurbishment of existing campus facilities and infrastructure. All Projects are project managed using a combination of internal resources and external consultants.
The major projects office also manages dealings in University land including development of same.

Contact us

Major Projects Team

Senior Manager Major Projects                                    
(Superintendent for all Projects)

Ken Suter
T. 08 8946 6309
F. 08 8946 7709
E. ken.suter@cdu.edu.au
Manager, Project Design & Documentation

Mal Logan
T. 08 8946 6217
F. 08 8946 7709
E. mal.logan@cdu.edu.au

Project Manager

Rik Jones
T. 08 8946 7737
F. 08 8946 7709
E. rik.jones@cdu.edu.au

  
Project Admin Officer
Vivien Dowling
T. (08) 8946 6862
F. (08) 8946 7709
E. vivien.dowling@cdu.edu.au
Administration Support
Jeff Apresto
T. (08) 8946 6273
F. (08) 8946 7709
E. jefferson.apresto@cdu.edu.au
 
Consulting Architect
Ranjith Dias
T.: 08 8946 6259
F.: 08 8946 7709
E. ranjith.dias@cdu.edu.au
Consulting Project Manager
Tom Lacey
T. 08 8946 6114
F. 08 8946 7709
E. tom.lacey@cdu.edu.au

Current projects

Current and proposed major capital works for CDU campuses.

Alice Springs Fire Mains Upgrade

Background: The project will install new fire mains and related services to recently revised standards.

Project Manager: Tom Lacey
Contractor: Asbuild (NT) Pty Ltd
Approximate value: $1.3m
Completion date: Third Quarter 2012

Update

Tender for construction of new Fire Mains has been awarded to Asbuild (NT) Pty Ltd and construction to commence 16 January 2012.

 


Current Projects - Casuarina (Quick Links)

Australian Centre for Indigenous Knowledge and Education (ACIKE)

ACIKE / BIITE - Student Accommodation

Student Accommodation - Increased needs

North Australian Centre for Oil and Gas

Casuarina Fire Main Upgrade

Health Workers Accommodation

Menzies School of Health Research Building

Library Refurbishment

 

Australian Centre for Indigenous Knowledge and Education (ACIKE)

 

Background

CDU and the Batchelor Institute for Indigenous Tertiary Education (BIITE) have established a collaborative venture, “The Australian Centre for Indigenous Knowledge and Education” to build a facility to deliver interactive learning with connections to 16 distant sites.

The building will incorporate state of the art IT enabled literacy laboratories, shared teaching spaces indigenous support and advisory staff front counters, gallery spaces showcasing indigenous activities and office space for the co-location of Indigenous research groups, academics and teaching staff.

This showcase building will be a multi level structure of approximately 3,000sqm. The building will maximize the opportunities for open air meeting spaces and use of natural ventilation and light.  This project will also include accommodation for approximately 30 students on the Casuarina site.

Project Manager: Mal Logan
Contact: 8946 6217

Contractor: Matrix Projects (Q’Ld) Pty Ltd

Approximately value: $24M

Completion date: Second Quarter 2012

Update

Generally the project is tracking well against program. Construction issues have been resolved quickly and have had minimal impact on the program. There have been no lost time injuries or accidents.

The majority of in ground services have been installed. The concrete floor slabs for blocks 1 & 2 are well underway as are the columns supporting the walkway for block 1. The walls for block 1 are currently being constructed. The water course for the creek and associated ponds have been mapped out and work has commenced on shoring up the banks.

There is a lot of activity on site with all the different trades. The logistics of moving supplies onto site and the removal of waste such as dirt spoil off of site appears to be well managed. The contractors are fully aware that the wet season is only a matter of months away and therefore working around the clock to ensure that buildings are at lock up stage prior to the onset of the wet season.

A tender was let for the design and construction of the Audio Visual and Video conferencing equipment for the complex.  The tender has been awarded and work as commenced on the design.  The installation of the equipment is expected to start in January 2012.

Tender for Furniture should be out late January 2012.

 

ACIKE / BIITE - Student Accommodation

 

ACIKE/BIITE Student Accommodation

 

Background

A component of the ACIKE/BIITE joint venture to build a thirty bed complex to house ACIKE Students. This will comprise apartment style buildings of two floors housing up to eight students per floor with shared facilities. The buildings will form part of the NFIH Complex.

Project Manager: Tom Lacey
Contact: 8946 6114

Contractor: ISIS Group Australia Pty Ltd

Approximate value: $3.3M

Completion Date: 1st Quarter 2012

Update

Construction is progressing in terms of timeline. Roofing is on all blocks. Blocks 1 and 2 are in the later stages of fit out. Completion is scheduled for the end of January 2012.

 


 

Student Accommodation - Increased needs

 

 

Background

The University has identified a need for additional student accommodation to meet current and future needs. It is addressing this issue on a number of fronts. The first involves building an additional two apartment style buildings of two floors. The layouts are variable allowing for some shared rooms. This project which is for two more blocks of 20 beds will be funded by external borrowings.

Project Manager: Ken Suter
Contact: 8946 6309

Contractor: ISIS Group Australia Pty Ltd

Approximate value: $3M

Completion date: 1st Quarter 2012

Update

Construction is progressing in terms of timeline. Roofing is on all blocks. Blocks 1 and 2 are in the later stages of fit out. Completion is scheduled for the end of January 2012.

 

 

North Australian Centre for Oil and Gas

Background

A feasibility to develop a Centre for Oil and Gas at the Casuarina Campus is currently being developed. Potential location is at the end of Technology Place adjacent to Purple 12.

Project Manager: Ranjith Dias
Contact: 8946 6259

Contractor: TBA

Approximate value: $5M

Commencement date: TBA

Update

Tender for construction has been issued and closes 31 January 2012. Initial planning for structural load testing building is being developed.

 

 

Casuarina Fire Main Upgrade

Background 

This project will progressively install new fire mains to recently revised standards.

Project Manager: Tom Lacey
Contact: 8946 6114

Contractor: Ausurv (Stage 1) Irwin Consult (stage 2)

Approximate value: $600,000 per annum

Completion date: Ongoing

Update

Preliminary Design work has been completed.

 

Health Workers Accommodation

Background

CDU has won a mandate from the Northern Territory Government Department of Health and Families to provide 20 units to house health care workers under a lease-back arrangement.

The scope includes construction of a twenty unit two-storey residential block in the student accommodation precinct to the northwest of the campus. The mix will consist of 8x35m² studio apartments and 12x40m² studio apartments, with two of the apartments adaptable for use by disabled occupants.

The development will include associated landscaping and a new parking area for 24 vehicles

Project Manager:Rik Jones
Contact: 8946 67737

Contractor: Mode Design

Approximate value: $100k

Completion date: 4th Quarter 2012

Update

A Tender for the Design & Documentation phase has been closed and awarded to Mode Design.

 

 

Menzies School of Health Research Building

Background

Menzies are to construct a new Research and Administration building on CDU Campus between the Library and the Chinese Garden.

Project Manager: Ken Suter
Contact: 8946 6309

Contractor: TBA

Approximate value: $18m

Completion date: TBA

Update

Documentation for construction and tender is approaching 95% stage with completion due in January 2012.

 

Library Refurbishment

Background

CDU is investigating freeing up space within the library for use as potential flexible learning and function areas.

As a result, alternative storage for some of the low-use print items is required. Major Projects has investigated a number of options to accommodate the material in RED 6.

Stage 1

The old dispatch area of Red 6 has been converted to book storage area and it is expected that books will be moved to the new area at the end of January 2012.

The installation of a De-humidifier will see the end of stage one.

Stage 2

Design Component

Design options for conversion of exterior balconies areas to student learning areas have been completed and preliminary estimates for costs obtained.

Tender for balcony work to be issued in January 2012.

Project Manager: Rik Jones
Contact: 8946 7737

Contractor: TBA

Approximate value: TBA

Commencement date: TBA

 

Pirates Club Refurbishment - Defects Period

 

Background:

With the recent opening of the Sport and Recreation complex, the gymnasium has relocated to their larger premises in the new building. The empty area left behind is now to be refurbished. This will create new change rooms, shower facilities and other ancillary spaces for the club administration and the Pirates Club home and away teams.

These improvements, including a new awning to the north facade will greatly improve the operations of the club. Other benefits will be rejuvenation in the overall use and increased amenity for the players and members.

Project Manager: Rik Jones
Contact: 8946 7737

Contractor: ISIS Group Australia Pty Ltd 

Approximate value: $700k

Completion date: End of July 2011

Update

August 2011

Project is now complete and occupied. Rectification of minor defects in progress.

 

 

Completed works

Proposed Work

View from Sports Oval

Existing Front Entry

Pirates Club exterior front entry ramp and stair progress

 

Pirates Club interior change rooms fitout progress

Northern Territory Medical Program and Allied Health Infrastructure (Pharmacy) - Defects Period

 

 

Background:

This complex will consist of two buildings, a purpose designed Pharmacy teaching facility and a purpose designed facility to train students in medicine as part of the Northern Territory Medical Program which in conjunction with Flinders University will deliver a full medical program in the Northern Territory.

The Pharmacy building will comprise two level s with a floor area of approximately 1000sqm. The Medical Program building is being built adjacent to the pharmacy building and will comprise three levels with a floor area of approximately 1800sqm. These buildings will have central cores of open space to take advantage of natural light and ventilation, in keeping with CDU policy of eco friendly buildings.

Project Manager: Ranjith Dias
Contact: 8946 6259

Contractor:  John Holland Pty Ltd

Approximate value: $16m

Completion date: Second Quarter of 2011

Update

Project is now complete and occupied. Rectification of minor defects in progress

 

.

 


Chiller Plant Upgrade - Defects Period

Background:

Current plant is at full capacity and the new proposal will comprise extension of the present building and installation of two new high efficiency chillers. The existing chillers will then be progressively replaced as part of a future project.  The Project is being funded under the umbrella of the ACIKE project.

Project Manager:  Tom Lacey
Contact: 8946 6114

Contractor: John Holland/Airducter/Wolpers Grahl
Approximate value: $5.2M

Completion date: Second Quarter 2011

Update

Project completed and fully operational.

 

 

PROJECTS UNDER DEVELOPMENT

EIF Bid for New Trades Training Facilities

Background: CDU is currently preparing a bid to cover the construction/upgrade of trade training facilities at Casuarina Campus.

 

 

 

National Rental Affordability Scheme (NRAS) Housing

Background: CDU has received NRAS Funding support for up to one hundred housing units to be built in Casuarina.


 

 

 

 

Palmerston Sports Precinct

Background:

The Northern Territory Government has unveiled the concept plans to deliver first class sporting facilities in Palmerston that will deliver significant upgrades across five sports. As a part of the $33 million parent project, the Palmerston Magpies AFL facilities at CDU’s Palmerston campus will receive a complete overhaul.

Four light towers, two grandstands housing 600 fans, an air-conditioned clubhouse, two new change rooms, an electronic scoreboard and major resurfacing work are all on the drawing board for the oval. Other upgrades include draining upgrades, new solid fencing to screen from the roadway and the extension of the existing car park to cater for 110 spaces.

Project Manager: Mark Dodt, Department of Construction & Infrastructure

CDU Contact: Tom Lacey - 8946 6114

Contractor: Halikos Construction

Approx Value: $10.4M

Completion Date: 2nd Quarter 2012

Update

Oval construction

Reconstruction of oval has been completed and new turf is developing well.

New Grandstand and club rooms is undergoing fitout.

New car park completed. Upgrade to existing car park is will take place when weather allows.

 

 

 

Palmerston Land Development

Background:

In 2008 Charles Darwin University commissioned a consultancy to determine the future use of the Palmerston campus land.  The study confirmed that the future needs of the University could be accommodated on approximately 40 hectares of land leaving approximately 70/80 hectares available for other purposes.  The consultancy recommended the land be subdivided for residential housing.  This recommendation was accepted by University Council and proposals for development were sought.

Project Manager: Ken Suter
Contact: 8946 6309

Contractor: CIC Australian Limited and Larrakia Development Corporation

Approx Value: $170M

Completion Date: TBA

Update

A consortium comprising CIC Australia Limited and Larrakia Development Corporation has been selected to develop the land.

Initial rezoning application lodged December 2010 and public hearing held March 2011. Rezoning has been approved. Development applications to be sumitted for Stage 1. Design work for roads and headworks is well advanced with work schedule to commence as soon as conditions allow.

 

 

 

Tenders on issue

Please contact 'tenders@cdu.edu.au' for further information

Tender Date closing
Construction and installation of new Fire Mains Casuarina Campus Anticipate issuance of tenders February 2012
Construction of a Twenty unit single bed accommodation block Anticipate issuance of tender for Construction 9th February 2012 and closes 8th March 2012
Tender T23.2011 Construction of roof & additions to existing Library balcony Closes 2pm Thursday 2nd February 2011
RFT19.2011 Construction and Installation of additional chilled water mains to service the new Australian Centre for Indigenous Knowledge and Education Closed - Awarded to Airducter Pty Ltd
Tender T18.2011 Loose Furniture and Fittings for student accommodation at North Flinders International House Closed - Jape Furnishing Superstore
RFT22.2011 Construction of the North Australian Centre for Oil and Gas

Closes 2 pm Tuesday 31 January 2011

T3.2011 Design, construction and Installation of night time Playing Lights, Alawa Oval No. 3 Casuarina Campus Closed - TBA
RFP4.2011 Design Development and Documentation for a 20 unit Accommodation Block at Casuarina Campus Closed - Awarded to Mode Design Corporation Pty Ltd
Tender T14.2011 Construction of Fire Mains at Alice Springs Campus Closed - Awarded to Asbuild (NT) Pty Ltd
RFP3.2011 Design and documentation of Fire Mains and Hydrants at Casuarina Campus Closed - Awarded to Irwinconsult Pty Ltd
Tender T5.2011 Design and Installation of Audio Visual and Audio/Teleconferencing Teaching Systems for the Australian Centre for Indigenous Knowledge and Education Closed - Awarded to Rutledge Engineering (AUST) Pty Ltd
RFP2.2011 Provision of Construction Design and Documentation Services for the North Australian Hydrocarbon Centre for Excellence Closed - Awarded to Lucid Consulting Engineers Pty Ltd

Tender T8.2010 Construction of teaching and administration buildings for the Australian Centre for Indigenous Knowledge and Education for the Charles Darwin University and Batchelor Institute of Indigenous Tertiary Education at the Casuarina campus

Closed - Awarded to Matrix Projects (Q’Ld) Pty Ltd
Tender T1.2011 Construction of 4 Multistorey Accommodation Units at Casuarina Campus Closed - Awarded to ISIS Group Australia Pty Ltd
Tender T12.2009 Sports Precinct Closed - Awarded to Sitzler Pty Ltd
Tender T2.2011 Refurbishment of Pirates Club, Casuarina Campus Closed - Awarded to ISIS Group Australia Pty Ltd
Tender T14.2009 NTMP & Pharmacy – Stage 2 Closed - Awarded to John Holland Pty Ltd
Chiller Building extensions:
Tender T1.2010 Chiller Plant Upgrade Closed - Awarded to Airducter Pty Ltd
Tender T2.2010 Chiller Plant HV-LV Transformer Supply Closed - Awarded to Wolpers Grahl Pty Ltd
Tender T3.2010 Chiller Plant Building Extension Closed - Awarded to John Holland Pty Ltd

Completed projects

Aged, Child Care and Health Care Support Workers Training Facility and Accommodation Blocks A& B- Alice Springs Campus

Project Manager:  Tom Lacey
Contractor: ASBUILD NT Pty Ltd
Approximate value: $3.4M
Completion date: December 2010

 

 

Refurbishment of MultiMedia Centre - Alice Springs Campus

Project Manager: Tom Lacey
Contractor: Scope Building 
Approximate value: $1.5m
Completion date: February 2011

 

 

 

 

 

Aged, Child Care and Health Care Support Workers Training Facility - Katherine Rural College

Project Manager: Tom Lacey
Contractor: Nightcliff Builders
Approx Value: $1.5M
Completion Date: June 2010

 

 

 

 

 

Sports and Recreation Precinct plus Medical Centre - Casuarina Campus

Project Manager: Ken Suter / Mal Logan
Contractor:  Sitzler Pty Ltd
Approximate value: $7m
Completion date: February 2011

 

 

 

 

Notifications

Major Projects is pleased to announce that the construction of buildings for the Australian Centre for Indigenous Knowledge and Education is about to commence.  The buildings will be part of the Blue Precinct at the Casuarina Campus.  The facility will be a key element in developing the collaboration between Charles Darwin University and Batchelor Institute of Tertiary Education and will create a state of the art learning environment for students and staff.

In the interests of safety, a barrier fence will be placed around the construction site.  This fence will be in place for the best part of a year.  Access to the site will be restricted.

Due to the nature of site and the scale of the project, Car Park Blue A will be closed for general parking.  Arrangements are being made to provide alternative parking spaces around the campus.  Car park Orange B will be designated as the new After Hours Secure Car Park.  Lighting is currently being upgraded and security cameras will be installed.  This car park will be for ticket and permit parking.  University Drive East will also be closed to traffic for extended periods of time.  This will allow constructors to install services within the road reserve.  There will also be a lot of heavy vehicle movements within this area.

A number of trees that are within the footprint of the new buildings will have to be loped or removed.  Some of these trees will be chipped and used as mulch around the campus.  Others will be transplanted into garden beds around the campus.  In conjunction with Landscape Architects, Grounds Staff, the Horticulture department and key stakeholders, a comprehensive landscaping plan has been developed to rehabilitate the area and to create a tropical environment.  Over $1m will spent on landscaping the area and adjacent buildings.

We appreciate your patience and tolerance during this period and apologise for any inconvenience that may arise during the project.  We believe we will deliver a fantastic facility for the University that will be  create a spectacular entrance to the campus.

If you have any queries in regard to this project, please do not hesitate to contact Mal Logan on ext.6217 or by email at mal.logan@cdu.edu.au

Below is a map showing location of works and the new Secure Car Park.

Location of workds and the new secure car part